We closed with great result the commissioning of TRICON 600 M which we had been delivered to a chemical plant in Pavlograd, Ukraine. On the first day we started the installed MWM TCG 2016 V12 C gas engine in idle operation after a few performed routine tests and on the following day the first synchronization was done. After that we started a 72-hour test run together with the MWM technician in order to finetune the parameters of CHP unit at full load with 600 kW electric power. Thanks to the precise implementation all performed tests was successful so our client was very satisfied too. We are looking forward the next order!